Professional Documents
Culture Documents
ISSN No:-2456-2165
IJISRT18JU151 www.ijisrt.com 86
Volume 3, Issue 6, June – 2018 International Journal of Innovative Science and Research Technology
ISSN No:-2456-2165
reduction of variables that are considered irrelevant to the structure is often the rain that interfere with the
purpose of the study. implementation process.
10. Work instructions or work directions that are not
B. Second Stage Data Collection delivered properly. Lack of training to the construction
The second stage of data collection is the team how to instruct or deliver work.
dissemination of questionnaires to the respondents who are 11. Lack of understanding of work methods and
competent and experienced at least 3 years in the field of procedures that are not executed correctly. The lack of
construction. Questionnaire distributed as many as 30 socialization conducted by the team engginer to the
pieces. construction team made the supervisor wrong in the
installation procedure of the kingpost structure.
C. Test Instrument Research 12. Coordination between divisions that did not go well
The research instrument test is conducted to test during the execution of the job of installing the kingpost
whether the result of the questionnaire that has been structure. Coordination meetings are not carried out
collected is valid and correct data. The instrument test in this routinely.
study using SPSS Version 20, validity test, reliability test,
multiple linear regression analysis, f test and t test. From 12 factors causing the slope of kingpost structure
obtained four dominant factors causing the slope of kingpost
IV. CONCLUSION structure of Indonesia's construction project 1.
From the result of the research, there are 12 factors Skill of the workforce that has not been qualified. Due
causing the slope of the kingpost structure on the work of to the absence of training on the workforce.
the structure of the project basement column of Indonesia 1: There was an error reading while using the work tool
(auto level dan total station) on the installation of the
1. Limitations of the number of skilled laborers in the kingpost structure. In this case fully the responsibility
execution of the installation work of the kingpost of the surveyor team.
structure. In this case due to lack of preparation to plan The presence of weather conditions, natural
how many experts are needed. disturbances that hamper work activities. At the time of
2. Skills / skills (skill) of the workforce that has not execution of the installation of kingpost structure is
qualified. Due to the absence of training on the often the rain that interfere with the implementation
workforce. process.
3. Lack of experience from human resources / staff in the Coordination between divisions that did not go well
implementation of the work of installing kingpost. Due during the execution of the work of the kingpost
to the lack of training of staff owned. structure. Coordination meetings are not carried out
4. Limitations of the number of experts in the direction routinely.
and supervision during the installation of kingpost. In
this case due to lack of preparation to plan how many REFERENCES
experts are needed.
5. Skill operator of heavy equipment that is not qualified. [1]. Bintang Nopirin, Bagaskara Mahayekti, Wibowo
Still found only one operator and if the operator can not Agung, Hidayat Arif. (2015). “Kajian Pemilihan
work due to illness or something else, there is only a Pekerjaan Basement Pada Bangunan Bertingkat Tinggi
deputy operator that can replace and the skill is still Menggunakan Metode Top Down Sebagai Inovasi
lacking, and it inhibits the installation work of the Metode Pelaksanaan (Studi Kasus: Proyek Sudirman
kingpost structure. Suites Hotel dan Apartment Jakarta”, Jurnal Teknik
6. The work tools used by the surveyor team have not Sipil, Universitas Diponegoro.
been calibrated or damaged. Found in the field when the [2]. Budi Santoso, S. M. (2016). Metodologi Penelitian,
job equipment work that should be re-calibrated but still “Metode Penelitian”, Modul Perkuliahan, Universitas
used. Mercu Buana.
7. Limitations on the number of work aids (auto level [3]. Choiriyah Siti. (2015). “Analisis Pekerjaan Basement
dan total station) during the execution of the installation (Pekerjaan Galian dan Diafrahma Wall) Dengan Alat
work of the kingpost structure. When performing the Berat Ditinjau Dari Aspek Teknis”, Jurnal Teknik Sipil,
installation work of the kingpost structure of a working Universitas 17 Agustus 1945 Surabaya.
aid there is only one pair, there should be one more as a [4]. Dipohusodo Istimawan. (1994). “Definisi Struktur
backup if the work tool has a problem or needs to be re- Kolom”, Departemen Pekerjaan Umum RI, Jakarta.
calibrated. [5]. Hidayat Arifal. (2013). “Analisis Kinerja Tim Proyek
8. There was a reading error when using the work tool Terhadap Keberhasilan Proyek”. Jurnal Teknik Sipil,
(auto level dan total station) on the installation of the Universitas Pasir Pangaraian.
kingpost structure. In this case completely the [6]. Idzurnaidi Ismail, Junaidi. (2014). “Identifikasi Faktor–
negligence and responsibility of the surveyor team, this Faktor Yang Mempengaruhi Keterlambatan
should not happen. Pelaksanaan Pekerjaan Pada Proyrk Pembangunan
9. The existence of disturbances of weather conditions, Gedung Di Kota Bukittinggi”, Jurnal Teknik Sipil,
natural disturbances that hamper work activities. At the Fakultas Teknik Sipil dan Perencanaan Intitute
time of execution of the installation of kingpost
IJISRT18JU151 www.ijisrt.com 87
Volume 3, Issue 6, June – 2018 International Journal of Innovative Science and Research Technology
ISSN No:-2456-2165
Teknologi Padang.
[7]. Mirnayani, ST, M. (2015). Manajemen Konstruksi.
Modul Perkuliahan, Manajemen Konstruksi, Modul 1,
Universitas Mercu Buana.
[8]. Mistra. (2012). “Struktur dan Konstruksi Bangunan
Tinggi Sistem Top and Down”. Edisi 1, Griya Kreasi,
Jakarta.
[9]. Prasetyo Bambang, Jannah Lina. (2005). “Metode
Penelitian Kuantitatif”, Edisi 1, PT. Raja Grafindo
Persada, Jakarta.
[10]. Project Mnagement Institute. (2016). “Construction
Extension to the PMBOK Guide”, Global Standard,
Campus Baulevard.
[11]. Sunyoto Danang. (2012). “Analisis Validitas dan
Asumsi Klasik”, Edisi 1, Gava Medika, Yogyakarta.
[12]. Tanubrata Maksum. (2015). “Pelaksanaan
Konstruksi Dengan Sistem Top–Down”, Jurnal Teknik
Sipil, Universitas Kristen Maranatha.
IJISRT18JU151 www.ijisrt.com 88